Kladno Power Plant (1996 – 2001)

Units 4, 5 and 6 – 2 x 135 MW + 1 x 70 MW

General designer of:

  • 2 x fluidized bed boiler with output 375 t/h of steam – supplier ABB Combustion

  • 2 x 135MW steam turbine ABB Stal VAX

  • Natural draft cooling tower

  • Two cells of forced draft cooling tower

  • Coal handling system

  • Ash handling system

  • Limestone handling system

  • Chemical water treatment

  • Control system ABB

  • Fire-fighting system

  • Stack

+

  • 1 x 70 MW gas TG (ABB GT8C) + heat recovery steam generator

Complete design and engineering services

Client: ABB


 